First subsea cable laid in 拢1.1bn Caithness-Moray project
The first of two sections of a high-voltage subsea cable has been laid in the Moray Firth as part of the 拢1.1bn Caithness-Moray transmission project.
A new ship purpose-built for the work, the NKT Victoria, laid the cable from Noss Head in Caithness to a midpoint in the firth.
Top Stories
The vessel has sailed to Sweden to reload the remaining cable to be laid from Portgordon in Moray to the end of the previously-laid cable later this month.
The cable will have capacity to carry up to 1,200MW of electricity generated by renewable energy projects in the north of Scotland to other parts of the country to power homes and businesses.
Top Stories
Led by Scottish and Southern Electricity Networks (SSEN), the 拢1.1bn Caithness-Moray Project is to be completed next year.
Top Stories
NKT Victoria, described by SSEN as "state-of-the-art", is being used for the first time.
It has capacity to hold 10,000 tonnes of cable and has remotely-operated vehicles for checking the laying of the cable in a trench ploughed by another ship in March.
In total, NKT Victoria will lay more than 70 miles (113km) of subsea cables.