Precedence tablesScheduling activities

A precedence table is a tool for scheduling activities in planning a project. It is based on the logic of what activities must follow other activities and what activities can run at the same time.

Part of Application of MathsMeasurement skills

Scheduling activities

Any project, whether it's cooking a meal or building a house, can be broken down into a set of separate activities.

Some activities cannot be started before others have been finished. For example, when building a house you cannot put in the windows before you have built the walls.

Tea making

Making a cup of tea involves the following activities:

Activity
ABoil the kettle
BPut a tea bag in a mug
CBrew the tea
DAdd milk
ActivityA
Boil the kettle
ActivityB
Put a tea bag in a mug
ActivityC
Brew the tea
ActivityD
Add milk

But there are constraints as some activities depend on each other:

  • Brewing the tea cannot happen before you have boiled the kettle
  • Brewing the tea cannot happen you have put a tea bag in a mug
  • Adding the milk cannot happen before you have brewed the tea

A precedence table helps you organise the activities and shows where there are constraints caused by dependencies. A dependency is where carrying an activity depends on another activity having been carried out.

Notice that a dependency only refers to the activity immediately before the activity in question.

ActivityDepends on
A
B
CA, B
DC
ActivityA
Depends on
ActivityB
Depends on
ActivityC
Depends onA, B
ActivityD
Depends onC

From this table you can see that either A or B could be started first as they do not depend on any other activity.